Installation
Gradually add plaster into clean water to mix
Build up 1mm coat to final thikcness
Apply second 1mm coat once first coat is frim to touch
Final Trowel once second coat has firmed up - lubricated Trowel with minimal water
Suitable for:
Dry undercoats - Use Thistle GypPrime, wet or dampen down first
Damp Undercoats - applied on the same day as the skim coat
Plasterboard - Use Thislte Bond-it on moisture resistant boards
Re-Skimming (Previously skimmed and painted surfaces) - Use with Thistle Bond-it
Flat smooth concrete - Use with Thisle Bond-it
2 Coats required
10mSq Per Bag
120 Minute approx finishing time
25kg to 11.5L Mixing
Hand application only